Phase I - Irrigation Project
Irrigation Project Timetable:
Irrigation System Designed, Reviewed and Approved by Seattle Parks Department --- 8/15/2003
North Laurel Hedge Removed, Land Graded and Prepared for New Native Plantings --- 8/1-30/2003
Irrigation System Installation Contracts Solicted (8/15), Opened (9/3), Contractor Ready to Begin (9/8)
Irrigation in 10/15: Initially North Hedge Area, South Planting Area and East Lawn installed .
Plantings in North Edge of Park --- 10/15-11/10/2003
Questions? Concerns? Let Us Know
friends@fgar.org
About the GAR Cemetery Park
Helpful Links
The GAR Calendar
2004-05 Contributors
About FGAR
Public Meeting Notes
Conceptual Plan Drawings
The Arborist's Report